Title: Water Level Measurement for the Verification of Reactor Building Health
Source: Tepco
Date: April 13, 2012

Purpose

To verify the reactor building health, we checked the levelness of the spent fuel pool (SFP) and the reactor well before commencement of cover installation work for removing fuels of Unit 4.

Published: April 14th, 2012 at 12:51 pm ET
By
Email Article Email Article
54 comments

Related Posts

  1. Tepco checking debris fallen to bottom of Reactor No. 4 — May move control rods — ROV to be sent into Spent Fuel Pool March 12, 2012
  2. Tepco: Cooling system back on at Spent Fuel Pool No. 4 July 1, 2012
  3. Tepco prepares to film Spent Fuel Pool No. 4 — “You can vaguely discern the fuel rods” says worker February 10, 2012
  4. TEPCO: Nuclear fuel rods in No. 4 spent fuel pool are “confirmed to be damaged” — First time damage revealed at any pool April 13, 2011
  5. “New problem”: TEPCO says No. 4 spent fuel pool may be leaking (VIDEO) April 26, 2011

54 comments to Tepco checking ‘levelness’ of No. 4 spent fuel pool

You must be logged in to post a comment.